Tidal-EC Project Update

Posted in News on .
ORE Catapult Blyth

The ORE Catapult Team has accelerated the design, procurement, assembly and commissioning of a new test rig to enable the Tocardo tidal device testing to begin in November 2016. The aim is still to start the testing in November and to finish in early February 2017. This project is expected to continue under current EC FP7 project until February 2017.